In the fourth quarter of 2021 from 15 to 26 November, officials of state supervision (control) of the State Service of Geology and Subsoil of Ukraine conducted a scheduled inspection of compliance with legislation in the field of geological study and rational use of subsoil «Mine Extraction».
Preliminary 3D model
In the third quarter of 2021, a preliminary 3D model of the Kapitanka Project was built based on the database, and Cr2O3, Ni, Co and Fe resources were calculated https://mineextraction.com/resources-and-modeling/
MINE EXTRACTION LLC has joined the network of the European Raw Materials Alliance – ERMA
The European Raw Materials Alliance ( https://erma.eu/) was established in 2020 as part of the EU Critical Raw Materials Action Plan and the publication of the EU Critical Raw Materials List 2020. The main goal of ERMA is to reduce the dependence of European consumers of mineral resources on third...
In the second quarter of 2021, the Drilling Program for a detailed geological and economic assessment of the Kapitanka Project was designed
Exploration Program – Kapitanka Project (mineextraction.com)
Mine Extraction LLC received form 3-gr for carrying out work on a detailed geological and economic assessment, registration number У-21-83/1 of March 31, 2021.
Negotiations with ANZAPLAN were held in March 2021. A proposal for Metallurgical test work of chromium ores of the Kapitanka Project using a combined test flow chart, which includes optical preliminary sorting and crushing of the ore to 100 microns.
In the fourth quater of 2020, a 3D model of the Kapitanka Project was built based on the database, with a cut-off grade Cr 2 O3 4 %.
Resources and Modeling – Kapitanka Project (mineextraction.com)